IPOH: The first two sets of Electric Train Service (ETS3) trains for KTM Bhd’s southern sector towards Johor have arrived in Malaysia, says Transport Minister Anthony Loke (pic).
He said the electric multiple unit (EMU) sets were currently undergoing technical tests, including dynamic and fault-free testing.
“If all the tests proceed smoothly, the trains are expected to begin operations by August.
“Apart from the first two sets, the remaining eight are being assembled in stages at the China Railway Rolling Stock Corporation (CRRC) plant in Batu Gajah, Perak.
“All 10 sets are expected to be completed and fully operational by early next year to enhance the country’s rail service capacity,” he said in a statement.
Earlier yesterday, he visited KTMB’s depot in Batu Gajah, which is co-located with the CRRC plant, Bernama reported.
Loke said more than 85% of workers at CRRC’s Batu Gajah plant are locals, reflecting strong potential for the transfer of knowledge and expertise to local talent.
“This high workforce composition not only contributes to the development of the national rail industry, but also puts Malaysia on a solid track to becoming a regional rail engineering hub in the future.
“The government will remain committed to enhancing the country’s public transport system to ensure the convenience and comfort of the people,” he added.