Audit Dept: A-G's Report reports uCustoms system 91.9% complete as of July 26, 2020


PETALING JAYA: The Auditor-General’s 2019 report (Series 2) had found that the uCustom's system’s physical development was at 91.9% as of July 26, 2020.

This clarification was made by the National Audit Department to The Star on Wednesday (Oct 6), in reference to an online report quoting the project’s vendor, Brilliance Information Sdn Bhd, as saying that the A-G's 2019 report had claimed only 27% of the project had been completed.

The Star Christmas Special Promo: Save 35% OFF Yearly. T&C applies.

Monthly Plan

RM 13.90/month

Best Value

Annual Plan

RM 12.33/month

RM 8.02/month

Billed as RM 96.20 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Align education with employment needs, says council
Dumpsite closures only a short-term fix, say groups
A struggle to match skills to jobs
More power in the hands of media
18 bankruptcies recorded each day
Think before you swipe, experts tell youths
Anwar slams criticism of Malaysia's humanitarian aid in Gaza
Meeting on Sabah's return of 40% revenue scheduled for Dec 19, says Hajiji
Bung’s son among four candidates identified for Kinabatangan, Lamag, says Sabah Umno chief
Ban on bringing pets into shopping malls remains in place, says Selangor exco

Others Also Read