Slow upgrade in need of booster shot


The new Seberang Jaya Hospital building under construction.

THE delay in the completion of the RM368mil upgrading project of Seberang Jaya Hospital has not gone down well with Penang Health Committee chairman Dr Afif Bahardin.

He said the project, which had already been delayed once before, was now expected to be ready only by the end of 2021.

He said the tender for 15 out of the 19 specialised jobs had not been awarded yet.

It is learnt that the main contractors were allowed to choose their respective subcontractors but the system was changed midway to an open tender system after Pakatan Harapan took over the Government in May last year in order to ensure transparency.

“I will bring up the issue to Finance Minister Lim Guan Eng to speed up the project,” he told reporters after a visit to the site.

Also present at the site was hospital director Dr Saiful Azlan Sharif.

The hospital is known to be packed with patients and upon completion of the project, its bed capacity will double to 630.

A multi-storey car park complex will also be built.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
News , Northern Region , bureaus

Next In Metro News

Waste deep in flat trouble
‘Permanent solution to flood issue in PJ needed’
Five stalls at Tg Bungah food hub told to clean up
Calls for COB to step in when low-cost flat management fails
JB eateries keep food prices steady
Penang’s ‘kapcai’ culture holds key to rail future
MBSP needs more funds for ageing infrastructure
Design roads for safety, not just enforce rules
Attitude cleanup a must to rid M’sians of dirty habit
Retention pond to bring flood relief to Taman Desa Seroja folk after 30-year wait

Others Also Read