Ongoing project: The one-way loop experimental phase in Petaling Jaya began in October last year. Phase 2 of the traffic system will be carried out over 18 months, starting this month. — filepic
PHASE 2 of the one-way loop in Petaling Jaya will see the work divided into four sub-phases lasting 18 months, said Bukit Gasing assemblyman Rajiv Rishyakaran in a press briefing on the traffic system’s progress.
In its “Proposed Construction Work Programme,” the first sub-phase (termed “quarter”) will see the western half of Jalan Utara, Jalan Timur and part of Jalan Sultan being developed from March till mid-July.