Phase 2 of traffic system in PJ to be carried out over 18 months


Ongoing project: The one-way loop experimental phase in Petaling Jaya began in October last year. Phase 2 of the traffic system will be carried out over 18 months, starting this month. — filepic

PHASE 2 of the one-way loop in Petaling Jaya will see the work divided into four sub-phases lasting 18 months, said Bukit Gasing assemblyman Rajiv Rishyakaran in a press briefing on the traffic system’s progress.

In its “Proposed Construction Work Programme,” the first sub-phase (termed “quarter”) will see the western half of Jalan Utara, Jalan Timur and part of Jalan Sultan being developed from March till mid-July.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read