ON the face of it, the timing of Citaglobal Bhd
’s recent announcement that it is teaming up with Tenaga Nasional Bhd
’s (TNB) generation arm, TNB Genco, to explore a power solution for a proposed data centre (DC) park in Gebeng, Kuantan, could have been better.
Over the past week, Malaysia’s DC ambitions have come under fresh scrutiny following tighter US restrictions on Chinese companies’ access to advanced Nvidia chips for use in DCs in countries such as Malaysia.
Adding to the uncertainty is US President Donald Trump’s latest threat to impose hefty taxes on American companies that build DCs overseas.
Citaglobal officials, however, say discussions with potential big-name DC players are continuing as usual, and have even intensified as the group moves closer to selecting a partner to develop and operate a DC campus at its proposed 247-acre site in Gebeng.
But first, how did Citaglobal, a diversified group with interests in engineering, construction, property, telecommunications and renewable energy, get into the DC business?
Group chief operating officer Datuk Aimi Aizal Nasharuddin says Citaglobal, together with its major shareholder Tiza Global Sdn Bhd, is uniquely positioned to offer an “energy-centric solution” to DC operators.
“It is about bringing together the key elements needed for a DC development – an approved site, a dedicated power supply and supporting infrastructure,” Aimi tells StarBiz 7.
At the heart of the proposed Gebeng development is Tiza AI Sdn Bhd, which has received approval from the Data Centre Task Force (DCTF) to build a DC. Tiza AI is 60%-owned by Tiza Global, the investment vehicle of Citaglobal executive chairman Tan Sri Norza Zakaria, who also holds his controlling 26.56% in Citaglobal.
Tiza AI’s approval is for the development of a DC with a maximum power demand of 1,300MW.
Elaborating on the proposed arrangement, Aimi says Citaglobal’s role is to provide the land and help put in place the supporting infrastructure, particularly the power supply.
Tiza AI’s DC approval is among the 27 approvals granted by the DCTF in August, all of which came with a requirement for an off-grid energy solution to power the DCs.
Under a non-binding memorandum of understanding signed on Nov 16, Citaglobal’s wholly-owned subsidiary, Citaglobal New Energy Sdn Bhd (CGNE), TNB Genco and Tiza AI agreed to explore a power supply solution for the proposed park.
Notably, CGNE and TNB Genco are envisaged to work together to develop a dedicated off-grid power solution, potentially combining gas-fired generation, solar photovoltaic facilities and battery energy storage systems.
Aimi explains that Tiza AI is expected to ink a deal with the international DC company to form a joint venture (JV). This JV, in turn, will purchase the land from Citaglobal, about 200 acres, for the DC campus.
The remaining 47 acres are intended to be leased to a separate JV between CGNE and TNB Genco, which would develop and operate the power-generation facilities and supply electricity to the DC campus.
“We recognised early on that power availability would be a key consideration for DC operators, so we factored that into the equation from the outset. We are in discussions with both Western and Eastern DC players, with the aim of bringing a recognised name on board.”
On the decision to sell the land to a single DC operator, Aimi says this would allow the site to be developed as one integrated campus, rather than being split among multiple operators.
“If all goes well, we expect an agreement to be signed in early December. The prospective buyer is expected to partner Tiza AI, the holder of the DCTF approval, to develop the DC campus,” he adds.
Citaglobal acquired the entire 247-acre site for RM90mil in January this year, equivalent to about RM8.40 per sq ft. As Gebeng is still an emerging DC location, the land is unlikely to command prices comparable to those in more established markets in Johor and Selangor.
Recent DC-related land transactions in Johor, Selangor and Negri Sembilan have ranged from RM105 per sq ft to RM150 per sq ft. Using a more conservative indicative value of RM80 per sq ft, the 200-acre parcel could fetch about RM697mil – a substantial premium over what Citaglobal paid for the entire 247-acre site.
Beyond the land sale and power-generation plans, Citaglobal is also looking to tap its construction, engineering and telecommunications businesses for project-related work as the development progresses, according to Aimi.
Citaglobal’s head of New Energy division, Datuk Chairil Nazri Ahmad, says Gebeng was selected for its proximity to a gas transmission pipeline and the coast, which could support both the proposed power facilities and the wider DC development.
He adds that TNB Genco’s involvement would give Citaglobal access to the utility’s power-generation expertise and boost confidence among prospective DC operators, although the two parties are still working out their respective roles in developing and operating the power facilities.
Chairil says the first phase of the proposed gas-fired plant is targeted for commissioning in the fourth quarter of 2029. In the interim, the group is exploring a temporary power solution using leased gas engines with a capacity of up to 200MW to meet the campus’ initial requirements.
A solar and battery energy storage solution is also likely to form part of the power mix, supplying electricity to the DC, with any excess potentially fed back into the grid.
On the potential impact of the latest US measures on the DC industry, Chairil says it is still too early to assess the full implications. “‘For now, our focus remains on advancing the Gebeng project, and bringing in a recognised name, as this could help attract further DC investment into Pahang.
“Beyond Gebeng, we see potential to replicate this approach at other sites in Pahang. We could also work with landowners through alternative arrangements, which would help reduce our upfront capital commitment,” he adds.
For a company that has so far attracted relatively little investor attention, the Gebeng venture could put Citaglobal more firmly on the radar as it seeks to establish a foothold in the power generation and DC ecosystem.
Whether this leads to greater investor interest will depend on how the plans take shape.
At last look, Citaglobal shares were trading at RM1.22 apiece, up 29.7% year-to-date and giving the group a market capitalisation of about RM687.33mil.