PETALING JAYA: Gamuda Bhd
has barely entered the fourth month of its financial year 2027 (FY27), yet the construction giant is already halfway towards achieving its ambitious full-year new contract wins target.
Its latest railway contract win in Taiwan has lifted year-to-date job wins to approximately RM17.1bil, representing 49% to 57% of management’s RM30bil to RM35bil target, according to MBSB Research.
Gamuda, through its 80%-owned joint-venture with Taiwan-based Feng Shun, was awarded a RM2.61bil design-and-build contract for the Keelung MRT underground civil works, with RM2.09bil attributable to Gamuda.
The package covers 2.4km of works and two underground stations between Nangang District in Taipei and Xizhi District in New Taipei.
The 7.4-year contract is expected to contribute to earnings from FY27.
The Taiwan contract carries an expected pre-tax profit margin of around 8%, with cost-plus terms limiting exposure to cost fluctuations, although underground execution risks remain.
Based on the margin guidance, TA Research estimated the project could contribute approximately RM167.2mil in pre-tax profit over the contract period.
This award falls outside the XizhiDonghu provisional works, leaving the remaining potential works unchanged at around RM6.5bil at the total project level.
These include the Xizhi-Donghu maintenance depot and Minsheng Line systems and trackwork.
Together with the earlier RM2.71bil attributable systems and trackwork award with MiTAC, Gamuda’s combined share of both Keelung contracts reaches RM4.8bil.
With this latest award, Gamuda’s construction order book was lifted to an all-time high of RM66bil.
This robust order book backlog implies about 4.4 times Gamuda’s FY26 construction segment revenue, providing its clear near-term earnings visibility, according to TA Research.
“Looking ahead, we see further upside potential for Gamuda to sustain its unbilled construction order book at approximately RM64bil to RM65bil by end-2026, supported by continued order book replenishment momentum across Malaysia, Australia and Taiwan.”
Meanwhile, RHB Research noted that Taiwan jobs now account for about 20% to 23% of Gamuda’s total order book.
“If we assume a burn rate of RM1.4bil per month from November to December, Gamuda’s outstanding order book by end-2026 may comfortably be around RM63.2bil, even if the group does not clinch any wins until end-2026, as per our calculation.
“Nonetheless, we envisage that there is still some room for new wins by end-2026, particularly from data centres and Australia’s railway sector (namely the Queensland’s Direct Sunshine Coast Rail Line).” RHB Research has not made any changes to its earnings estimate as the latest job win is within its FY27 job win.
It said a key catalyst would be if Gamuda could demonstrate a faster-than-expected sizeable uplift in margins as major data centre projects progress, with RM7bil worth of new data centre wins secured so far in 2026 along with an earlier-than- expected win for jobs for the Northern Perak Water Supply Scheme.
“Key downside risk is a prolonged period of high input costs.”
RHB Research, MBSB Research and TA Research have a “buy” call on Gamuda.
According to MBSB Research, Gamuda remains its top construction pick, backed by its record order book and improving earnings visibility.
“Management expects construction revenue and pre-tax profit to grow by around 60% year-on-year in FY27, with 90% of revenue already covered by existing contracts.
“Meanwhile, property sales are targeted to more than double to RM7bil in FY27.
“This will be underpinned by a RM9.4bil launch pipeline across Vietnam, Singapore and Malaysia over FY27 to FY28.