KUALA LUMPUR: Gamuda Bhd
said its unincorporated joint venture with Taiwan-based Feng Shun Construction Co Ltd has been appointed the main contractor for the design and build of Keelung Underground Mass Rapid Transit (Station SB32 to Station SB33) Turnkey Project in Taiwan by the Department of Rapid Transit Systems.
Gamuda, which has an 80% majority stake in the JV, said the contract is valued at NTD21.02bil (about RM2.61bil), giving it a RM2.09bil share of the contract sum.
The project, which will run for 2,700 days or 7.4 years, will entail 2.4km of underground works located across Nangang District (Taipei City) to Xizhi District (New Taipei City), including two underground stations.
Gamuda said in its announcement to Bursa Malaysia the project is expected to contribute positively to the revenue and earnings of Gamuda Group for the financial year ending July 31, 2027, until the completion of the project.