Global push to speed up DC grid access


DC developers are increasingly turning to so-called behind-the-metre power generation to bypass years-long waits for grid connections and get their facilities running sooner. — Bloomberg

NEW YORK: Governments around the world are looking for ways to speed up data centres’ (DC) connections to local power grids, seeking to curb a growing reliance on on-site natural gas plants that threatens to increase emissions from the boom in artificial intelligence, according to BloombergNEF.

DC developers are increasingly turning to so-called behind-the-metre power generation to bypass years-long waits for grid connections and get their facilities running sooner.

Those systems typically rely on natural gas, potentially reversing years of progress in cutting emissions from electricity generation.

A report published by BloombergNEF yesterday examined proposed policy efforts in the United States, Europe and Asia to accelerate grid connections and limit the environmental impact of DC growth.

“Powering DCs via the grid today would result in lower carbon dioxide emissions than using on-site gas in the United States and Europe,” the report’s authors wrote. — Bloomberg

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Business News

Swift Haulage quarterly earnings rise
United Plantations 3Q profit improves
Call to widen SME financing options
SSBB secures RM146.8mil DC projects
Empire Premium profit jumps as outlet expansion gathers pace
S P Setia sharpens focus on earnings resilience
Whitman banks on AI�to train next generation
Rivertree to buy Q Centre Management
FBM KLCI extends decline to close lower
Ringgit eases against the greenback

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read