Mitrajaya accepts RM42.81mil fourth variation order for data centre project


KUALA LUMPUR: Mitrajaya Holdings Bhd’s wholly-owned subsidiary, Pembinaan Mitrajaya Sdn Bhd, has accepted a fourth variation order worth RM42.81mil for data centre main works in Kuala Lumpur.

In a filing with Bursa Malaysia, the group said the variation order, accepted on Dec 10, 2025, was issued by NEXTDC Sdn Bhd and covers Stage 1 Phase 3 of the data centre project.

Following the latest variation, the revised contract sum now stands at RM844.66mil.

The works under the fourth variation order are expected to be completed by July 28, 2026.

Mitrajaya said the fourth variation contract is expected to contribute positively to the group’s earnings and net assets for the financial years ending Dec 31, 2025 and 2026.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Mitrajaya , data centre , NEXTDC

Next In Business News

Berjaya Food to exit loss-making Kenny Rogers Roasters operations, retain 5% stake in JV
Public Packages acquires Penang land for RM55mil mixed-use project
KJTS secures RM37.39mil cleaning services contract
MOF targets net direct tax collection of RM199bil for 2027
Greatech’s 3Q net profit jumps 77%, order book stands at RM1.98bil
Kelington Group posts higher 3Q earnings on revenue growth
Chin Hin Group Property, PMCK to develop private hospital in Melaka
Star Media’s 9M26 revenue rises 23% to RM195.1mil
Asian chip stocks roar back, FBM KLCI rebounds
CIMB Securities identifies 20 potential additions to expanded FBM KLCI

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read