Uzma achieves COD for its 50MWac large-scale solar plant


PETALING JAYA: Uzma Kuala Muda Sdn Bhd, an indirect wholly owned subsidiary of Uzma Bhd, has achieved the commercial operation date (COD) for its 50MWac large scale solar photovoltaic plant under the Large Scale Solar (LSS) Cycle 4 project on Sept 25.

The plant, which is located in Sungai Petani, Kedah, is Uzma’s first venture into asset ownership and development of an LSS plant, pursuant to a power purchase agreement entered into between Uzma Kuala Muda and Tenaga Nasional Bhd in August 2021.

“Uzma Kuala Muda achieved the project’s financial close date on July 14, 2023 and within a record 10 months of starting physical construction in November 2023, the project was able to hit its COD milestone,” said Uzma.

Uzma said the achievement of the COD is expected to contribute positively to the future earnings of the group, adding that the plant is expected to generate clean energy that will mitigate approximately 1.8 million tonnes of carbon dioxide equivalent emissions throughout the duration of the plant’s operations.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Uzma , solar , PV , Large Scale Solar , LSS

Next In Business News

Tan Chong, Saike explore EV battery pack localisation in Malaysia
Ringgit ends mostly higher against major currencies, but weakens vs US dollar
MBSB Bank provides RM29.6mil financing to Bisajuta for Sabah infrastructure projects
Reservoir Link secures PPA for 200MWac solar facility in Sarawak
MASkargo, IAG Cargo and Qatar Airways Cargo complete first customer shipment trial
Citi appoints Yik Ping Chong as Malaysia commercial banking head
Binastra records 93.4% revenue growth in 1H27, declares 4.0 sen dividend
FBM KLCI falls amid broad selling, ringgit sinks to one-month low
Malaysia strengthens aerospace position as local players move up value chain
Moody’s: 14-17GW additional power capacity to require up to RM95bil investment over 10 years

Others Also Read