It’s the rakyat who will pay for power plant delays


AS this article goes to print, Tenaga Nasional Bhd will be in the final stages of commissioning the 1,000 MW coal-fired power plant in Manjung, Perak. The special-purpose vehicle undertaking the project is 12 days behind schedule and has to pay a fine of about RM500,000 per day, which comes to about RM6mil, to TNB under the terms of the power purchase agreement (PPA).

But a delay of 12 days for a project that runs over three years is no real delay. In large projects that are dependent on cashflow such as constructing and commissioning a power plant, delays running into months can make the project completely not viable financially.

Play, subscribe and stand a chance to win prizes worth over RM39,000! T&C applies.

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Business , 1mdb tenaga

Next In Business News

Malaysia's palm oil-based biodiesel push to add 300,000 tons in demand, says MPOB
Iran war exposes cost of Asia's fossil fuel reliance
S P Setia to launch final Ferrous phase in Alam Impian with RM75.4mil GDV
Bank Rakyat declares 18% dividend, totalling RM534.7mil for FY25
Asian stocks climb to pre Iran war levels on de escalation hopes
CIMB, DBKL partner to empower MSMEs, boost KL economic activity
Singapore dollar to outperform peers as yuan link deepens
PETRONAS to supply excess fuel to Australia as leaders vow closer energy ties
China records 5% GDP growth in 1Q26
TSMC Q1 profit jumps 58% to record, beats expectations

Others Also Read