It’s the rakyat who will pay for power plant delays


AS this article goes to print, Tenaga Nasional Bhd will be in the final stages of commissioning the 1,000 MW coal-fired power plant in Manjung, Perak. The special-purpose vehicle undertaking the project is 12 days behind schedule and has to pay a fine of about RM500,000 per day, which comes to about RM6mil, to TNB under the terms of the power purchase agreement (PPA).

But a delay of 12 days for a project that runs over three years is no real delay. In large projects that are dependent on cashflow such as constructing and commissioning a power plant, delays running into months can make the project completely not viable financially.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Business , 1mdb tenaga

Next In Business News

South Korea shares rise ahead of Nvidia earnings
Asia-Pacific region to grow 4.2%; AI boom to cushion headwinds
Japan's Nikkei reverses course to rise as chip shares track South Korea�rebound
Commodity vessel transits through Strait of Hormuz hit three-month low�data shows
Lego sales rise as World Cup products draw new customers
New Sinopec boss presses reset for world's biggest oil refiner
Asia-Pacific airlines to maintain growth despite cost headwinds - S&P
VW CEO faces workers angry over his plan to cut 100,000 jobs
China taps AI for tax system modernisation drive
Dollar struggles for traction as markets weigh Iran sanctions, Treasury buybacks

Others Also Read