Ministry explains early award of power plant to 1MDB


PETALING JAYA: The Energy, Green Technology and Water Ministry (KeTHHA) came up with an explanation on why it awarded a 2,000-megawatt (MW) gas-fired power plant project to 1Malaysia Development Bhd (1MDB) seven years ahead of its commissioning in 2021, which is unprecendented in the local industry.

KeTHHA, in a written reply to parliament last Thursday, said that 1MDB was awarded the project to be located in Malacca through direct negotiations because of its track record, to maintain a reserve electricity margin of 25.8% level for that year and after taking into consideration the national interest of the country as a whole.

Win a prize this Mother's Day by subscribing to our annual plan now! T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Business , 1MDB , power , Maximus Ongkili

   

Next In Business News

Sentral REIT records 1Q net income jump to RM19.9mil
Go Hub secures Bursa Malaysia's approval for listing on ACE Market
FBM KLCI drifts sideways in search of fresh leads
Grandtech Cloud Services welcomes Justin Tiew Senn as new APAC vice president
UOB posts small drop in quarterly profit, confident of maintaining key margin level
Singapore's MAS asks DBS to identify reasons for disruptions, The Strait Times reports
Ringgit opens lower against US$ amid Middle East tensions
CTOS prospects remain bright despite court ruling
FBM KLCI stays firm, but profit-taking pressures mount
S&P, Dow extend closing streaks despite Disney drag

Others Also Read