KNH nears phase 1 completion of RM2.5bil wastewater project


The Kuching centralised wastewater management system project.

KUCHING: The Kumpulan Nishimatsu-Hock Seng Lee (KNH) consortium is in the final stages of negotiations with Sarawak state authorities on the Kuching centralised wastewater management system project package 2 contract.

As the turnkey contractor, the KNH consortium is currently at the tail-end of completing the RM530mil package 1, which got off the ground in October 2008. As at March 31, 2014, about 92.6% of package 1 had been completed, according to the Sarawak Sewerage Services Department.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Business , Business , Hock Seng Lee

Next In Business News

FBM KLCI ends flat but ekes out weekly gain
Indonesia expects palm oil export levy collection to jump about 31%
Maybank, Singapore Manufacturing Federation partner to drive JS-SEZ growth
Gold climbs to near three-month peak after US Treasury move
Malaysia Airports' July international passenger traffic up 9.3%
Japan's Nikkei logs worst week in over a month on Middle East uncertainty
CapitaLand and IOI Properties close to buying Singapore US$1.9bil office towers
Malaysia targets Arm collaboration chips to enter production by 2030
Oil set for second weekly rise as unsettled US-Iran war crimps supply
Solar, wind electricity used to support computing bonanza

Others Also Read