SUKE construction records 87% overall progress


KUALA LUMPUR: The Sungai Besi-Ulu Kelang Elevated Expressway (SUKE) construction work has recorded an overall progress of 87 per cent as at end-2020, supported by full completion of the CB3 package.

SUKE deputy general manager Dr Zarulazam Eusofe said the CB3 package, which connects to Jalan Taman Putra with Jalan Merbau near Ampang town, was the first package completed 100 per cent from eight construction packages for the SUKE project.

The Star Christmas Special Promo: Save 35% OFF Yearly. T&C applies.

Monthly Plan

RM 13.90/month

Best Value

Annual Plan

RM 12.33/month

RM 8.02/month

Billed as RM 96.20 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Business

Kelvin Tan Aik Pen returns to Innoprise Plantations as managing director
Bursa Malaysia ends morning session easier
Malaysia's official reserve assets at US$124.12bil as at end-Nov 2025
MSC appoints co-group CEOs
Asian stocks set for strongest annual jump in eight years on AI bets
China's factory activity edges back to growth in December, private PMI shows
Oil slips as Brent heads for longest stretch of annual losses in 2025
Bursa Malaysia poised to wrap 2025 on a multi-year high
Ringgit opens higher as US$ slips after FOMC minutes
Trading ideas: Genting, Sunview, Apex Healthcare, Cypark, Citaglobal, HeiTech Padu, Insas, Propel Global, Solar District, TT Vision, UEM Sunrise

Others Also Read