SUKE construction records 87% overall progress


KUALA LUMPUR: The Sungai Besi-Ulu Kelang Elevated Expressway (SUKE) construction work has recorded an overall progress of 87 per cent as at end-2020, supported by full completion of the CB3 package.

SUKE deputy general manager Dr Zarulazam Eusofe said the CB3 package, which connects to Jalan Taman Putra with Jalan Merbau near Ampang town, was the first package completed 100 per cent from eight construction packages for the SUKE project.

Save 30% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 9.73/month

Billed as RM 9.73 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 8.63/month

Billed as RM 103.60 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Business

Sentral REIT appoints Tay Hui Ling as CEO
Mega First to acquire 12.5% stake in Stenta Films for RM33.10mil
DXN inks MoU with Apex-Brasil to explore Brazil, eyes US$50mil investments
F&N to focus on innovation, diversification and transformation
Mulpha International invests US$20mil in Hong Kong's Sun Hung Kai bond programme
Ringgit breaches 4.04 level against US dollar after OPR maintained at 2.75%
Capital A’s Teleport to raise US$50mil via perpetual securities
Apex Healthcare to be delisted on Jan 27
Prudential to raise stake in Malaysia life insurer holding firm to 70% for US$377mil
BWYS shareholders approve RM67mil property disposal, RM94.5mil land acquisition

Others Also Read