SUKE construction records 87% overall progress


KUALA LUMPUR: The Sungai Besi-Ulu Kelang Elevated Expressway (SUKE) construction work has recorded an overall progress of 87 per cent as at end-2020, supported by full completion of the CB3 package.

SUKE deputy general manager Dr Zarulazam Eusofe said the CB3 package, which connects to Jalan Taman Putra with Jalan Merbau near Ampang town, was the first package completed 100 per cent from eight construction packages for the SUKE project.

Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

   

Next In Business

Oil settles higher on Mideast supply concerns
Wall St closes up as megacap tech stocks rally
Wall St Week Ahead: Investors punishing earnings disappointments
Majuperak forms renewable energy partnership with Shizen Group
Blackstone, KKR mortgage REITs stung by office debt challenges
Indonesia adds a pinch of chili against the US dollar with rate hike
Powering on data centres
Singapore’s growth trajectory remains intact
Rising data centre ability
Financial maturity vital with introduction of Account 3

Others Also Read