Vietnam weighs delaying nuclear power plants beyond 2035


HANOI: Vietnam may be forced to delay its first nuclear power plants until after 2035, complicating efforts to boost energy security and economic growth.

The Ministry of Industry and Trade has proposed a start date of 2037 or 2038 for the Ninh Thuan 1 nuclear plant, and 2039 or 2040 for Ninh Thuan 2, according to a draft revision to the nation’s power development plan published this week for consultation.

Vietnam Electricity Group, or EVN, has submitted a pre-feasibility study to the finance ministry for Ninh Thuan 1, and the existing plan calls for the plant in south-central Vietnam to become operational between 2030 and 2035.

However, planners, including Russian partner Rosatom, have assessed it’ll take a minimum of 12 years to set up the project once a feasibility study is completed.

EVN is still proposing an earlier completion in 2034 or 2035 if conditions are favourable. The accelerated timeline for Ninh Thuan 2, which is being developed by Petrovietnam and a South Korean partner, is 2035 or 2036.

"Setting shorter and ambitious timelines for expensive and emerging technologies such as nuclear power can increase the risk of shortfall in future power-generation capacity,” said Hanh Phan, an analyst at BloombergNEF.

The potential delays cloud the outlook for Vietnam’s push to develop nuclear power to help cut its reliance on imported fossil fuels, a vulnerability brought to the fore this year by soaring energy prices caused by the US-Iran war.

Utilities from France to the US have struggled to build reactors on time. Vietnam’s industry and trade ministry hasn’t said when it’ll make a final decision.

The revised plan also includes delays to liquefied natural gas projects. LNG-fired power capacity is expected to reach about 4.3 gigawatts by 2030, less than half that envisioned under the existing plan. Of the 18 proposed LNG projects in the country, only one is on schedule and just two have begun construction, the ministry said last month.

Vietnam plans to add 22.5 GW of LNG power projects by 2030, but BNEF expects only around 4 GW to be commissioned by that year, Phan said.

The revised plan also scraps the addition of about 6 GW of offshore wind capacity by 2030, although solar capacity is expected to rise by around 10% to 81.6 GW. - Bloomberg

 

 

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Vietnam , nuclear , power , delay

Next In Aseanplus News

53 undocumented migrants held in Johor swoop
Three RMAF officers among six charged in 96.2kg meth trafficking case
Sarawak polls: EC checking on next steps if GPS wins on Nomination Day
Indonesia sees silver lining in new US tariffs despite global backlash
Permutation bet lands Selangor couple RM24.4mil Toto jackpot
Two workers hurt in blast, fire at Kerteh waste processing plant
New Zealand’s ruling coalition falls just short of majority, needs centrist Opportunity to govern
Abdul Gani Patail's passing a loss of prominent figure in Malaysia's legal fraternity, says SLS
Bursa Malaysia expected to extend recovery after volatile week
The search for Vietnam's stolen pets at wet markets and slaughterhouses

Air Pollutant Index

Note: API is calculated based on 24hr running average of the most dominant parameter.

Highest API Readings

    Select State and Location to view the latest API reading

    Others Also Read