HANOI: Vietnam may be forced to delay its first nuclear power plants until after 2035, complicating efforts to boost energy security and economic growth.
The Ministry of Industry and Trade has proposed a start date of 2037 or 2038 for the Ninh Thuan 1 nuclear plant, and 2039 or 2040 for Ninh Thuan 2, according to a draft revision to the nation’s power development plan published this week for consultation.
Vietnam Electricity Group, or EVN, has submitted a pre-feasibility study to the finance ministry for Ninh Thuan 1, and the existing plan calls for the plant in south-central Vietnam to become operational between 2030 and 2035.
However, planners, including Russian partner Rosatom, have assessed it’ll take a minimum of 12 years to set up the project once a feasibility study is completed.
EVN is still proposing an earlier completion in 2034 or 2035 if conditions are favourable. The accelerated timeline for Ninh Thuan 2, which is being developed by Petrovietnam and a South Korean partner, is 2035 or 2036.
"Setting shorter and ambitious timelines for expensive and emerging technologies such as nuclear power can increase the risk of shortfall in future power-generation capacity,” said Hanh Phan, an analyst at BloombergNEF.
The potential delays cloud the outlook for Vietnam’s push to develop nuclear power to help cut its reliance on imported fossil fuels, a vulnerability brought to the fore this year by soaring energy prices caused by the US-Iran war.
Utilities from France to the US have struggled to build reactors on time. Vietnam’s industry and trade ministry hasn’t said when it’ll make a final decision.
The revised plan also includes delays to liquefied natural gas projects. LNG-fired power capacity is expected to reach about 4.3 gigawatts by 2030, less than half that envisioned under the existing plan. Of the 18 proposed LNG projects in the country, only one is on schedule and just two have begun construction, the ministry said last month.
Vietnam plans to add 22.5 GW of LNG power projects by 2030, but BNEF expects only around 4 GW to be commissioned by that year, Phan said.
The revised plan also scraps the addition of about 6 GW of offshore wind capacity by 2030, although solar capacity is expected to rise by around 10% to 81.6 GW. - Bloomberg