Boeing 787 output hiccups reemerge at assembly sites


NEW YORK: Boeing has pushed some factory work on the 787 Dreamliner to the uncovered tarmac outside its assembly plant in Washington state in an effort to keep churning out the popular plane at a rate of one every three days, according to people with knowledge of the situation.

At the same time, the sources said, at least 16 Italian-made fuselage sections for the 787 have stacked up in a Boeing hangar in Wichita, Kansas, rather than being shipped directly to the factory, a sign of changes in the production process.

The unusual shifts, details of which have not been previously reported, are partly a response to unfinished jobs building up as 787s move along the assembly line and partly an effort by Boeing to speed up the factories.

Boeing spokesman Marc Birtel said outside work is not unusual when unfinished jobs build up along the assembly line, and is not unique to the 787 line. He said the company has reduced the backlog of jobs since January, though the sources said the situation has gotten worse.

The company is trying to streamline 787 production and cut costs while hitting its target of delivering a record 110 Dreamliners this year, up from 65 in 2013.

Investors are counting on smooth Dreamliner production to lift Boeing's stock, which has fallen 12 percent this year on fears that production could falter as Boeing speeds up the factories and introduces new models, and that global demand for new airplanes will taper off after years of heady growth.

Boeing stock was up 0.13 percent, to $119.99 (£71.53), in afternoon trading on the New York Stock Exchange.

In some sense, the production problems reflect the aerospace sector's record-setting strength. Order books at Boeing and rival Airbus are bulging, with about 10,000 planes valued at more than $700 billion combined. Both companies are speeding up output of their best-selling models.

The 787, an innovative, fuel-saving long-range jet, the most popular version of which carries a list price of $257 million, has garnered 1,057 orders since it hit the market in 2004. Most are made at Boeing's factory in Everett, Washington, with a smaller line in North Charleston, South Carolina.

But North Charleston also puts together midbody fuselage sections from pieces shipped by Alenia, a unit of Italy's Finmeccanica . North Charleston workers install wiring and other components and ship the finished pieces to Everett or their local assembly line for final assembly.

The production process did not previously involve storage of midbody section pieces in Wichita, according to the sources. Boeing sold its operations there in 2005, and has put the last of its facilities there up for sale.

Boeing said the rerouted fuselages are stored for a couple of weeks in Wichita to ensure they are available when needed in North Charleston. No assembly work is being performed in Wichita, and the rerouting is due to be phased out soon, the company said.

Meanwhile, the 787 assembly line still has a large volume of unfinished jobs, according to people familiar with the production.

The jobs, known as "travelled work" because they are moved to the next part of the assembly line, surged early this year when Boeing increased 787 production to 10 a month from seven. Boeing stock dropped when the problems surfaced, and the company hired back hundreds of contract workers it had laid off to attack the problem.

In May, Boeing said it had largely eliminated travelled work and gave South Carolina workers a bonus for cutting the backlog.

But since then, Boeing has dispatched teams to complete installation of galleys, lavatories, seats, stowage bins and carpet while the planes are parked on the flight line, according to two people with knowledge of the situation. The work is normally performed in the factory.

Employees at the plant in Everett are working mandatory 10-hour days and weekends to keep up, said the people, who were not authorised to speak publicly about the company.

One source said several hundred workers are assigned to the teams doing final assembly after planes have left the factory.

"We've had hundreds of those guys coming to the flight line almost on a round-the-clock basis to perform all the travelled work," said one of the sources.

Despite the problems, Boeing has met its production targets, delivering 30 787s in the latest quarter and 56 so far this year through July, including a new stretched version of the plane.

"While it’s not optimal, it happens on every airplane programme and is certainly not unique to the 787," said Birtel, the Boeing spokesman. - Reuters

Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

   

Next In Business News

Global manufacturing activity recovery to continue gradually into 2024 - S&P Global
Country Garden plans to present debt revamp plan in second half, sources say
Oil prices on track to snap two-week losing streak
MAA Group sells entire 58% stake in Turiya for RM52.86mil
Majuperak, Shizen to explore solar photovoltaic development in Perak
Asia stocks rise, yen plumbs 34-year low as BOJ stands pat on rates
Fernandes: AirAsia Group to be listed on Bursa Malaysia in September
Spritzer clarifies mistaken identity in insider trading report
Berjaya Corp denies involvement in Forest City Casino talks
Malaysia's PPI higher by 1.6% in March 2024

Others Also Read