Project 3B plant ops date delayed due to transfer from 1MDB to TNB


As it stands, Project 3B is one of the two major power plants whose construction works have been delayed.The other is Project 4A, which is a contract to build a new 1,000 MW-1,400 MW combined cycle gas turbine power plant in Johor, awarded to a consortium comprising TNB and SIPP Energy Sdn Bhd

PETALING JAYA: The earliest date of commercial operation for the 2x1,000 MW coal-fired power plant in Jimah, coded Project 3B, in Negri Sembilan, has been postponed to June 2019 from the original October 2018.

The delay was to facilitate the transfer of 1Malaysia Development Bhd’s (1MDB) entire shareholding in the project to Tenaga Nasional Bhd (TNB).

Win a prize this Mother's Day by subscribing to our annual plan now! T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Business , TNB , Tenaga , 1MDB , power plant , energy , Project 3B

   

Next In Business News

Asian currencies set for weekly fall; stocks firm on US rate cut bets
KL Sentral Station redevelopment project to commence year-end - Loke
Malaysia's March manufacturing sales value grows 1.4% to RM158.4bil
Oil set for weekly gain as demand signs, geopolitics seen as positives
Asia stocks rally on renewed global rate cut optimism
Daiso invests RM1bil in new global distribution centre
IPI up 2.4% in March 2024 but below forecast
Malaysia end-April palm oil stocks rise 1.85%, MPOB says
FBM KLCI nearly flat at midday
UOB Malaysia's FY23 operating income hits record RM4.6bil, pretax profit RM1.9bil

Others Also Read