Cable repair on Penang Bridge to be completed by Friday (June 25), two weeks ahead of schedule


GEORGE TOWN: The high-voltage cables on Penang Bridge that caught fire several months ago will be fully repaired and operational on Friday (June 25).

Tenaga Nasional Berhad (TNB) chief grid officer Datuk Husaini Husin said this was ahead of the scheduled completion date of July 6, despite the repair crews having to deal with rough sea conditions.

Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

Defence Ministry mulls reviewing fly-past SOP
Copter pilot Sivasutan cremated in Sitiawan
Keep people like Gilley out!
‘New EPF initiative won’t have significant impact on property sector’
‘Casino licence issue a lie’
Forging mutual ties for progress
Littoral combat ship probe still ongoing, says Azam Baki
UM to tighten processes, guidelines after Gilley controversy
‘No rewards for lying down on the job under SSPA’
‘Where is mummy going?’

Others Also Read