A-G's Report: Defence Ministry did not impose claims or late charges of RM116.54mil to company supposed to deliver its ship


PETALING JAYA: The Defence Ministry failed to impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s report.

At the same time, the report found that the advanced payment made for the ship exceeded the actual work progress by 21.1%.

The report said that the company was supposed to deliver the LCS 1 on April 2019, but as of Dec 31,2019 or 245 days later, it had yet to be delivered.

The report added that as of June 30 this year, although the scheduled delivery of the ship had exceeded 12 months, the ministry had not issued a letter to the company demanding late charge penalty but had merely issued a reminder to the company on the delay.

The RM9bil contract for the delivery of six ships was from Oct 2013 to Oct 2023.

The report said that according to the contract, the ships were to be delivered in stages from April 2019 to June 2023.

In response, the ministry said that as of June 10 or 435 days after the delivery of LCS1, the late payment charges stood at RM217.5mil.

It said it had issued a notice of claim of RM180mil to the company because of a capping on the claim.

They added that as of July 1, the status of the progress of the LCS was 56.7% compared to the planned 85.7% - a delay of 29.1% or 31 months.

The report said that as of Dec 31, advanced payments of RM910mil or 63.8% of progress payments have been made, although it was only at 42.7%.

The report also found that late payment charges of RM15.04mil were not imposed on the company that was to supply 24 Lightweight Multiple Launcher - New Generation (LML-NG) between June 2018-September 2018.

The audit found that 20 of the 24 launchers were delivered between 28 –171 days late.

The ministry said it will act on the matter after getting a response from its legal department.

The A-G report also highlighted that nine armoured personnel carriers (APC) purchased by the ministry did not meet the specifications of the United Nations (UN), as they were unarmed.

The APCs, which were used in a UN peace mission in Lebanon, were first purchased by the Malaysian government, with the UN to reimburse the government.

Because the vehicles were not equipped with the Remote Control Weapons Station, the government lost out on RM2.2mil in reimbursements.

The ministry said that the APCs passed the Final Acceptance Test and could be used for the United Nations Interim Force in Lebanon (UNIFIL) and that the non-specifications were only from the weapons systems.

Get 20% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 11.12/month

Billed as RM 11.12 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 9.87/month

Billed as RM 118.40 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Nearly 40% of EPF members meet RM390,000 basic savings target, Parliament heard
S'wak cops seize over 15 tonnes of bird's nests worth RM81.8mil in series of raids
Selangor records highest number of baby dumping cases
KK, Penampang, Sepanggar need redelineation, says Upko president
List of 54 companies for Jana Wibawa projects came from PMO, not Finance Ministry, Tengku Zafrul tells court
New-generation MyKad may be used to ID eligible buyers of subsidised cooking oil, Dewan Rakyat told
Footballer dies after suspected lightning strike in Melaka
Eden at Botanica CT and AIA Pension and Asset Management enter MoU to advance retirement preparedness in Malaysia
Johor polls: 12,710 police personnel to cast early ballot tomorrow
Tengku Zafrul arrives to testify in Muhyiddin's graft trial

Others Also Read