Tunnel ‘breakthrough’ at Ampang Park MRT station


KUALA LUMPUR: As the tunnel-boring machine (TBM) made a “breakthrough” at the future Ampang Park MRT station, hundreds of staff cheered as if a football goal had been scored.

They also grabbed the chance to take pictures in front of the completed tunnel.

The breakthrough took exactly nine months to complete, spanning a distance of 1.8km from the crossover box at Hospital Kuala Lumpur.

The TBM tunnelled an average of 7m a day through different geological formations.

A breakthrough is when the TBM completes the tunnelling of a certain portion of the whole underground alignment.

This breakthrough was the ninth and final one of the year.

“It is an important milestone to the project. Every time there is a breakthrough, we know a certain percentage of the project is completed. It is important to follow the schedule, ” said MRT Corp Sdn Bhd strategic communications and stakeholder relations director Datuk Najmuddin Abdullah.

The Ampang Park station is part of the MRT Sungai Buloh- Serdang-Putrajaya (SSP) Line, which is expected to serve a two-million catchment population.

Excited over boring machine: Workers cheering the breakthrough of the tunnel boring machine at the Ampang Park MRT station.Excited over boring machine: Workers cheering the breakthrough of the tunnel boring machine at the Ampang Park MRT station.

Najmuddin said that as of October, overall progress of the construction was at 63.5%, while overall progress for tunnelling works was 66.8%.

With the latest breakthrough, six tunnel sections have been completed with another three in progress.

Another two sections are to start within the next two months, with all tunnelling expected to be completed by July of next year.

Among the challenges faced included tunnelling beneath major roads in the city, tunnelling beneath railway tracks, and even below sewerage pipes.

At the shallowest parts, the tunnel was just 12m below the surface, a challenge to ensure no damage occurred to buildings and roads among other things.

Senior project manager of the underground works, Alex Terry said that a combination of mitigation measures had to be taken before mining and during the drive work.

He said this included extensive ground treatment works, utility relocation and the piling removal of existing structures.

The first phase of the SSP line is expected to begin operations in July 2021, while the second phase is expected to start operations in 2023.

The SSP Line spans a distance of 52.2km with 35 stations, of which 11 are underground.

Article type: metered
User Type: anonymous web
User Status:
Campaign ID: 18
Cxense type: free
User access status: 3
   

Did you find this article insightful?

Yes
No

100% readers found this article insightful

Next In Nation

Former Terengganu MB, wife test positive for Covid-19
Sabah MACC detains tradesman over bribery attempt
Allowing low-risk patients to be home quarantined will ease hospital congestion, says Health DG
Disabled community applaud and hopeful on Permai assistance package
Socso committed to implementing programmes under Permai aid package
Number of Covid-19 cases should stabilise in a week, says Health DG
Seremban 2 court complex to be sanitised after 16 detainees contract Covid-19
Storehouse next to temple in Taman Desa Ria, PJ, gutted
526 cases recorded in Sabah a result of mass screenings of plantation workers
Covid-19: PM visits MAEPS 2.0 integrated hospital

Stories You'll Enjoy