AG Report: Unqualified contractors blamed for delay in Mindef's Sukhoi service centre project


  • Nation
  • Monday, 21 Nov 2016

Sukhoi Su-30MKM fighter jets doing a fly-by at Padang Merdeka Kuching, Sarawak. - Filepic

PETALING JAYA: The construction of a RM73mil service technical centre (STC) for the maintenance of Sukhoi SU-30MKM fighter aircraft at TUDM Gong Kedak, Terengganu Air base was less than satisfactory, according to the 2015 Auditor-General's Report (Series 2).

The report revealed that a slow construction progress during the first 10 months which resulted in a takeover by a nominated sub-contractor on Jan 15 last year.

Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

Cops on hunt for Tanah Merah house break-in suspect
Lorry driver dies in hydraulic oil drum explosion in Sibu
218 out of 338 dilapidated school reconstruction projects in Sabah completed, says Fadhlina
Hearing on June 27 for Zahid’s case
Guided by Loh and order
Cast your vote for StarProperty’s Readers’ Choice
Making the best of a bad situation
Unity govt may announce candidate two days earlier
Eruption of Mount Ruang volcano puts paid to travel plans
Nabila: Let nature take its course on parenthood

Others Also Read