The third series of the Report drew attention to the RM12.65mil overruns in building the IPKBN complex, which was originally estimated to cost RM77.59mil.
"Based on the contracts, the construction of Phase 1 of the complex started on Feb 15 2006 and was to have finished on Feb 12 2008, while Phase 2 started on Jan 14 2008 and was to have finished on June 29, 2009.