Suai Water Treatment expansion ahead of schedule


MIRI: The RM64mil expansion of the Suai Water Treatment Plant is progressing smoothly and expected to be completed by mid- December this year.

Sarawak Public Utilities Minister, Datuk Amar Awang Tengah Ali Hassan said the progress of the works was 62.11 percent compared to the scheduled 61.66 percent with a start date of Aug 8 2011 and completion target of Feb 7, 2013.

Save 30% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 9.73/month

Billed as RM 9.73 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 8.63/month

Billed as RM 103.60 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Nation

Parents: Give us more time to gauge readiness of our kids
New entry tests for Year One to be unveiled soon
Early Year One entry may strain schools further
‘Diagnostic tests are harmless’
Zara Quairina inquest: Ex-principal unaware of students' written statements
Police corporal killed in Ipoh motorcycle-car crash
Kinabatangan by-election: Voters torn between loyalty, local sentiment as polling day nears
Kedah declares Feb 1 public holiday for Thaipusam
Six including company owner remanded four days in graft probe
MIC hasn't left BN, says Zambry

Others Also Read