Phase One of Tanjung Manis water supply project going smoothly


SIBU: Work on phase one of the Tanjung Manis water supply project is currently being undertaken by seven contractors at a cost of RM590mil.

The 24-month construction period started in November last year and is scheduled for completion in November next year.