In a note on Thursday, the research house said Hartalega's first two plants’super structures are ready and production lines are currently being installed.
"The first two lines are on schedule to commence operations by end-November and December respectively. The NGC will be built on 112 acres of leasehold land along Jalan KLIA. Hartalega will be commissioning two plants of 12 lines each, with completion slated for 4Q2015.