RTS link construction progressing at 77.61% as at May 31


An artist’s impression of the Rapid Transit System (RTS) Link in Bukit Chagar in Johor Baru. — Photos: Malaysia Rapid Transit System

JOHOR BARU: Construction of the Rapid Transit System (RTS) Link Project between Johor Baru and Singapore is progressing as scheduled at 77.61% as at May 31, 2024.

In a statement today, Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) said the maintenance depot, one of the main components of the railway infrastructure located in Wadi Hana, has achieved progress of 82.14% and is scheduled for system installation by year end.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
RTS , JB , transportation

Next In Business News

Toyota still has the drive
Hurdles in DBS’ Alliance Bank bid
Metals keep shining bright
Retailers get a lift from Sara
iCents eyes Asean
Ringgit likely to trade within narrow range next week ahead of BNM OPR decision
Reading the market signals
Breathing new life into forgotten spaces
Urban harmony: Can stakeholders row together?
China’s gold rush continues

Others Also Read