When does time for delivery of vacant possession of property start?


The result of both the GJH Avenue and PJD Regency cases is that it is now uncertain as to when the period for delivering VP starts from. With these conflicting decisions, we will have to wait for the Federal Court to resolve the question.

WHEN one buys housing accommodation from a developer in Malaysia, the terms of the sale and purchase agreement with the developer are prescribed by law (S&P), specifically the Housing Development (Control and Licensing) Regulations 1989 (HDR 1989).

Depending on the type of development, a developer is required to deliver vacant possession of the property (commonly referred to as VP) within 24 months or 36 months from the date of the S&P. If the VP is delivered after the prescribed period, the developer needs to compensate the purchaser for every day of the delay, unless extension of time is granted under the HDR 1989.

The Star Christmas Special Promo: Save 35% OFF Yearly. T&C applies.

Monthly Plan

RM 13.90/month

Best Value

Annual Plan

RM 12.33/month

RM 8.02/month

Billed as RM 96.20 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Next In Business News

Jasa Kita acquires 55% stake in SPPH�
PetGas to pre-pay up to RM706mil in jetty usage charges at Pengerang LNG terminal
Colform awards 4 contracts worth RM1.33mil
Hextar Global acquires three fertiliser companies for RM120mil
Ringgit climbs to strongest level against US dollar since early March 2021
Solarvest acquires ACE-Market listed SDCG for RM42mil
CBH Engineering wins data centre job worth RM130mil
JPG consolidates JPG Greenergy Ventures, strengthens renewable energy strategy
Kimlun bags three construction jobs totalling RM618mil
PMCK records RM5.83mil 2Q profit, declares 0.12 sen dividend

Others Also Read