Pertama Ferroalloys to achieve full production in June


Executive chairman Hirotaka Suzuki(pic) said the US$400mil plant was currently producing 18,000 tonnes per month and operating below 80% of installed capacity.

KUCHING: Pertama Ferroalloys Sdn Bhd will raise its output of manganese alloy products to 22,000 tonnes per month when its smelting plant in Samalaju Industrial Park, Bintulu, is ramped up to achieve full production in June.

Executive chairman Hirotaka Suzuki said the US$400mil plant was currently producing 18,000 tonnes per month and operating below 80% of installed capacity.

Win a prize this Mother's Day by subscribing to our annual plan now! T&C applies.

Monthly Plan

RM13.90/month

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Business , Pertama Ferroalloys , Samalaju , AML , production , June ,

   

Next In Business News

UOB Malaysia launches Masterclass to help businesses for EU's Carbon Border Policy
Oil climbs after Israel strikes Gaza, truce talks continue
Overcapacity talk won't affect MNCs' commitment
Nintendo expects to sell 13.5 mln Switch units this year
M&A Securities and Newparadigm back Siab’s acquisition of Taghill with rights issue
Saudi Aramco maintains dividend despite lower net income in Q1
Pekat unit in negotiations over purchase of stake in electrical power solutions firm
Asia shares rise on rate cut bets; Aussie slips on RBA
UBS reports first profit since taking over Credit Suisse
Amazon to spend nearly US$9bil to expand cloud infra in Singapore

Others Also Read