Why is the Land Public Transport Commission not following the original route that was approved under the Greater KL Plan, which was displayed in Putrajaya? Y.S. Yee, TTDI KL

Several alignments were proposed for the Sungai Buloh-Kajang corridor, underscoring the severe need for an urban rail system to serve the areas along the line. All alignments suggested earlier, however, are proposals which are subject to feasibility studies prior to implementation. The current Sungai Buloh-Kajang alignment was proposed by Syarikat Prasarana Negara Bhd in 2006. Feasibility studies and engagement with local authorities have been carried out by Prasarana since then to determine the optimum alignment. Final approval of the alignment will only be given by the Government after the three-month public display period which ends on May 14, 2011 and after feedback from the public have been given due consideration.

The MRT will be running very close to my house. How far must the house be away from the line before the commission (SPAD) will acquire my property? What are my rights and options? I am genuinely concerned. Yeong, TTDI, KL

The law stipulates that the alignment must be at least 6m away from the boundary of a piece of property. Land acquisition is governed by the Land Acquisition Act 1960 and the agency handling it is the Department of the Director-General of Land and Mines. SPAD does not have authority over land matters.

The current notices placed in public places along the mass rapid transit (MRT) corridor is governed by Sect 4 of the Act. The Act states that the land administrator of that particular state must put up notices as close to the land as possible to inform the public that the general land area within a 60m corridor has been gazetted for possible land acquisition. It does not mean that all the land will be acquired.

It is only after May 14 when the public display period ends and after all feedback has been received and consultations undertaken with various bodies that the actual plots to be acquired will be ascertained. At that stage, under Sect 8 of the Act, individual owners of the plots to be acquired will be notified directly. The land administrator will hold hearings for the owners. Adequate time will be given for affected landowners to search for alternative properties. Compensation for any land acquired will be determined by the Valuation Department and will be set at market prices.

SPAD, in evaluating the proposed MRT alignment, will ensure that as little land as possible will be acquired for the project.

Since we already have the light rail transit (LRT), why are we not extending this LRT into new areas? Why must we build the MRT which cost so much more? Michael, Balakong

The Government is extending the LRT line for the Kelana Jaya Line, from Kelana Jaya to Putra Heights and for the Ampang Line, from Sri Petaling to Putra Heights over a total of 35km. The existing KTM Komuter system was also extended from Sentul to Batu Caves, a distance of 7km.

Nevertheless, the number of places where extensions of the LRT lines can serve will be limited and any further extension of the current LRT lines will end up making journey times very long and unattractive to commuters. In terms of capacity, the LRT will quickly reach its maximum limit while the MRT, which generally has 50% more capacity, will be able to comfortably satisfy the transportation needs of the Klang Valley for many years into the future.

The Klang Valley needs to increase its urban rail coverage. The Klang Valley now has low rail-based public transport coverage compared with most public-transport oriented cities. It has less than 20km of rail per million population, compared to public transport oriented cities such as Singapore, Hong Kong and London which have an average of 40km of rail per million population. This gap can be closed via the development of an MRT network. The rail network which includes the MRT, LRT, KTM Komuter and Monorail will form the backbone of the public transport network in the Klang Valley.

How is SPAD going to improve the feeder buses? Will there be more buses with a regular time table? As far as I know, the current lot of feeder buses are irregular, never on time and never around when one is needed. Kumar, KL

The Sungai Buloh-Kajang MRT Line will take five years to complete. While feeder bus routes for the line have been proposed and are currently on display to the public, SPAD will nevertheless conduct a thorough study on the demand and routing of such services. This will be completed ahead of the completion of the line and the feeder bus network will be ready when operation begins.

Why is the MRT serving the high-class areas of TTDI, the Curve, Bandar Utama and Subang USJ? They don't need the MRT. Ganesan, PJ

It is not a question of serving high-class areas or not. In fact, the locations named in the question cannot be lumped together as being “high-class areas”. The Curve is a popular shopping centre, making it a major activity point and destination for many people, thus justifying the need for public transport. Bandar Utama and Subang USJ are huge residential areas which can also do with good public transport services while the proposed Sungai Buloh-Kajang MRT alignment which runs along the periphery of TTDI will also serve densely-populated areas on the other side of the alignment, such as Damansara Kim, Damansara Utama and other neighbouring housing areas.

It is hoped that once an efficient, reliable, user-friendly, affordable and safe public transport service in the form of the MRT is made available, car owners may be convinced to leave their vehicles at home or at stations and ride the train into the city or to wherever their destinations may be.

Who and how is the route of the MRT decided? What are the criteria? Chandran, KL

Many factors come into play when an MRT alignment is determined. The overarching principle is benchmarked against the following:

1. Regional level where fixed points are identified where the line must serve. These are determined by factors such as serving areas where there is no rail service at the moment, serving densely-populated areas, serving activity centres such as the central business districts, shopping centres or office blocks, and serving areas where there is potential future growth.

2. Engineering, social and environmental factors such as constructability, ridership, land acquisition, social and environmental impact, journey times and integration with existing systems

3. Micro level where local details are taken into consideration via public feedback

What is your advice on leadership practices to the youth, the future leaders of Malaysia? Polly Tan, KL

Aspire to change the world. Along the way, lead by example, practise what you preach and always be guided by honesty and accountability in your actions.

Because the MRT costs so much, can SPAD hold more public forums before embarking on it? I understand work is expected to start by the middle of the year. Gurmit, PJ

SPAD is taking all the necessary steps to reach out to the public. SPAD organised an open day for the public on Feb 13 and this was immediately followed by public displays of the railway scheme and plans at seven locations. This will be on until May 14. During this period, SPAD will also be organising sessions with the various communities along the proposed alignment to provide information about the project and to gather feedback. Members of the public can also visit the Klang Valley MRT project website at www.kvmrt.com.my or call the helpline at 1800 88 2828 for more information. Feedback can be emailed to feedback@kvmrt.com.my.

What is the role and functions of SPAD other than building the MRT? Does it have the power to reorganise and restructure what we today call our public transport or lack of it? Matthew, Cheras

Firstly, let me clarify a misconception. SPAD is not the party building the MRT. That role is carried out by Prasarana. SPAD is the supervising agency for the MRT project where it is to ensure the system being developed will serve the people's needs and interests.

SPAD was set up on June 3, 2010 by the Government to ensure the creation of a safe, reliable, responsive, accessible, planned, integrated, affordable and sustainable land public transport system to enhance economic growth and quality of life.

Prior to the setting up of SPAD, there were at least 15 agencies involved in the public transport sector. This led to some overlapping and inconsistencies in policies. With the setting up of SPAD, the powers to draw up policies, plan, regulate and enforce laws, rules and regulations concerning land public transport came under one roof. This enables the commission to become the sole government agency to champion public transport. For more details, go to www.spad.gov.my

Who is going to pay for the entire MRT project, and if it is the Government, how do you think they will get that money? Jahabar, Seremban.

The Klang Valley MRT project will be fully funded by the Government. A special-purpose vehicle under the Finance Ministry will be set up to advise, manage and raise the funds for the project through a mixture of financial instruments as well as direct funding from the budget.

Because tax-payers' money is being used to fund the project, there is a great emphasis on exploring all possible options to lower the cost. One interesting mechanism being used is the value management study (VMS) where an independent party is scrutinising project plans and ensuring that the optimum value is derived. The VMS will also help with the early identification of non-fare box revenue. Non-fare box revenue is important as about one third of the revenue of Hong Kong's mass transit rail system is not from ticket sales while in Tokyo, the non-fare revenue is as high as 80%.

Article type: metered
User Type: anonymous web
User Status:
Campaign ID: 1
Cxense type: free
User access status: 3
   

Next In Business News

Bermaz profit raises to RM133.9mil in FY21
Palm oil reverses course to trade up 1% on stronger US soyoil
Uzma, Petra Energy JV wins onshore petroleum E&P contract in Sarawak
Ipmuda sells PJ property to Kerjaya Prospek, eyes expansion into renewable energy and healthcare businesses
Tenaga, plantations power KLCI sharply higher
Malaysia maintains CPO export tax at 8% for July
FDI slips to lowest since 2009 due to pandemic
Vehicle sales in May doubled on-year but minimal sales seen in June
Malaysia's Carsome weighs US listing with SPAC as option
Pound tumbles as virus resurgence clouds hope for UK recovery

Stories You'll Enjoy


Vouchers