Last sections of Ho Chi Minh Expressway to be completed by 2025


A section of the Ho Chí Minh Expressway passing through the Tay Nguyen (Central Highlands) province of Kon Tum is put into operation. — VNA/VNS

HANOI: An additional 170km of Ho Chí Minh Expressway is to be built and completed by 2025, reported the Transport Ministry.

According to the ministry’s report, the Ho Chi Minh Expressway project, which started in 2000, has completed 2,488km out of its total length of 2,744km, and 258km of branch routes.

With the remaining 256km in five ongoing component projects, the ministry expects some sections to be completed by 2025.

Specifically, the Chon Thanh - Duc Hoa section with a length of nearly 73km passing through four southern provinces of Binh Phuoc, Binh Duong, Tay Ninh and Long An, has total investment of VNĐ2.3 trillion (US$92.94 million) with a roadbed of 12.25m wide and road surface of 11.25m wide.

To date, all three construction and installation packages have been completed, two of which were started in January 2024.

Basic progress meets requirements for the section to be completed by the end of 2025.

The Cho Chu - Trung Son Junction section, with a total length of nearly 29km passing through two northern provinces of Tuyen Quang and Thai Nguyen has two lanes, 9m-wide roadbed and 6m-wide road surface, designed with operational speed of 60km per hour and invested with VNĐ1.6 trillion (US$66.93 million).

After having the investment project approved, the Ho Chí Minh Expressway Project Management Unit (PMU) has drawn out construction design, estimated expenses and selected a construction contractor to start construction in the first quarter of this year. The section is expected to be completed next year.

The Hoa Lien - Tuy Loan section in Hoa Vang District of Danang City is invested VNĐ2.1 trillion (US$84.75 million) with total length of 11.5km and designed with four lanes and a roadbed width of 22m.

The project began construction at the end of August 2023 and is expected to be completed in 2025.

Up to now, the locality has only handed over land for building 2.5 out of 11.5km of expressway and one out of 20km of collector road.

The slow handover is affecting the project progress which has just met 0.5 per cent of the contract value.

The Rach Soi - Ben Nhat and Go Quao - Vinh Thuan sections has total investment of VNĐ3.9 trillion ($157.4 million) with total length of nearly 52km passing two southern provinces of Kien Giang and Bac Lieu, and designed with two lanes and road surface of 12m.

The PMU is completing procedures to start the construction in the first quarter of this year.

Particularly, the Co Tiet - Cho Ben section with total length of over 87km passing through three northern provinces and cities of Phu Tho, Hanoi and Hoa Binh, has completed a pre-feasibility study report and submitted to the Ministry of Transport for appraisal and approval.

The Ho Chi Minh Expressway has a starting point in northern Cao Bang Province and an ending point at southern Ca Mau Province.

Under the Law on Planning, the expressway is integrated into the road network for the period 2021-30, with vision to 2050, approved by the Prime Minister in Decision 1454/QĐ-TTg dated Sept 1, 2021. — Vietnam News/ANN

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Vietnam , Ho Chi Minh , highway

Next In Aseanplus News

Asean News Headlines at 10pm on Thursday (Dec 18, 2025)
China says arms trade with Cambodia, Thailand unrelated to border conflict
NParks investigating Singapore influencer over dog abuse allegations
Thailand and Laos discuss economic cooperation plan to boost trade to US$11bil by 2027
Sri Lanka arrests three men for burning elephant alive
Jail for man in Singapore who struck domestic helper with knife, kicked police officer and stole mobile phone
Body found in bag believed to be missing Ampang woman, say cops
Three Songkhla districts warned of flash floods and mudslides
Jail for man and his mother after he misappropriates over S$1.2mil from firm’s bank account in Singapore
Nadma coordinating immediate action in six flood-hit states, says Anwar

Others Also Read