Transport Ministry: KLIA2 construction never experienced cost overruns


KUALA LUMPUR: The construction of Kuala Lumpur International 2 (KLIA2) never experienced a cost overrun although it ultimately cost RM4bil to build instead of the initial RM1.7bil, the Dewan Rakyat was told.

"This project had never experienced a cost overrun. The reason was due to the additional scope for the new design concept for KLIA2, or the specific needs of the takeholders such as airlines and the Government," said the Transport Ministry in a written response to Ariff Sabri Abdul Aziz (DAP-Raub).

Article type: metered
User Type: anonymous web
User Status:
Campaign ID: 53
Cxense type: NA
User access status: 3
Subscribe now to our Premium Plan for an ad-free and unlimited reading experience!
   

Next In Nation

No kidnappings for organs in Johor, say cops
Stage set for community-based tourism operators to showcase Sabah’s hidden treasures
House rental agent arrested for scam in KK
Case management for Rosmah's appeal in solar case set for Nov 14
20 soldiers detained for robberies at sea, says Home Ministry
Syabu most seized drug in KL, says police
18 detained in connection with kidnapping Palestinian man
King grants audience to Turkish Parliament Speaker
Social media, messaging apps linked to over 600 sexual crimes against children below 18, Parliament told
Over RM2.5bil lost to phone scams since 2018, says Home Minister

Others Also Read