KNH nears phase 1 completion of RM2.5bil wastewater project


The Kuching centralised wastewater management system project.

KUCHING: The Kumpulan Nishimatsu-Hock Seng Lee (KNH) consortium is in the final stages of negotiations with Sarawak state authorities on the Kuching centralised wastewater management system project package 2 contract.

As the turnkey contractor, the KNH consortium is currently at the tail-end of completing the RM530mil package 1, which got off the ground in October 2008. As at March 31, 2014, about 92.6% of package 1 had been completed, according to the Sarawak Sewerage Services Department.

The Star Christmas Special Promo: Save 35% OFF Yearly. T&C applies.

Monthly Plan

RM 13.90/month

Best Value

Annual Plan

RM 12.33/month

RM 8.02/month

Billed as RM 96.20 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
Business , Business , Hock Seng Lee

Next In Business News

SC, IRB to strengthen inter-agency cooperation, safeguard financial ecosystem
CPO prices to remain range-bound between RM3,800 and RM4,100 a tonne in Jan 2026- MPOC
Bursa Malaysia extends upward momentum at midday
Bank of Japan raises interest rates to 30-year high, signals more hikes
Oil set to close lower for second straight week
Mah Sing, KLK to jointly develop Kulai industrial project
Samaiden to develop 99.99MWac solar PV facility in Segamat
Malaysia's exports rise 7% to RM135bil in Nov
United Malacca among top gainers in early trade after posting higher 2Q earnings
Ringgit opens slightly higher vs greenback on softer US policy outlook

Others Also Read