Court: No power to grant extension


Take them to task: According to the liquidated damages clause, condo buyers can claim 10 per annum of the purchase price for the delay.

KUALA LUMPUR: The Housing Controller has no power to grant an extension of time to developers who delay the completion of housing projects, the High Court has ruled in a landmark judgment.

This means a housing developer has to pay compensation to the affected buyers for delays in the delivery of vacant possession.

Save 30% OFF The Star Digital Access

Monthly Plan

RM 13.90/month

RM 9.73/month

Billed as RM 9.73 for the 1st month, RM 13.90 thereafter.

Best Value

Annual Plan

RM 12.33/month

RM 8.63/month

Billed as RM 103.60 for the 1st year, RM 148 thereafter.

Follow us on our official WhatsApp channel for breaking news alerts and key updates!
News , bureaus

Next In Nation

Alumni reconnect at SOBA Prestige business gathering
Ministry to recruit 20,000 teachers
Don’t wait for MHIT to get basic insurance, M’sians urged
EPF for medical coverage a relief
Boy dies three months after mongoose bite
GLICs translate Madani values into action
Enforcement at all levels the only way ‘country can be fixed’, says Anwar
1,399 housing projects revived under task force
Penang safeguards its best food
Johor mall gets community together for record-breaking feat

Others Also Read