Common Tower Tech counter claims RM131.8m from Weida


KUALA LUMPUR: A telcommunication towers construction JV between Weida (M) Bhd and Common Tower Technology Sdn Bhd (CTT) in 2005 which went sour has seen both parties filing lawsuits against each other.

In the latest development, CTT is counter claiming from Weida's unit Weida Works Sdn Bhd for the construction of the towers and also RM131.84mil as wrongful interest imposed by Weida.

To recap, Weida Works and CTT inked a JV deal on June 22, 2005 and first supplementary JVA on March 23, 2006 to undertake the telecommunication infrastructure projects in Sabah.

Under the JVA, Weida Works was to fund and build telecommunication towers in the projects.

CTT would then secure the tower sites and licence for the towers on these sites to mobile telecommunication operators for licence fees.

CTT would then share such licence fees income received from both the original operators and new operators with Weida at an agreed ratio.

On May 23, 2017, Weida said a notice of arbitration which was issued and filed with the Kuala Lumpur Regional Centre for Arbitration (KLRCA).

Weida Works alleged CTT breached the JVA for not paying Weida Works its entitled share of all licence income from the new operators for RM23.43mil which was Weida Works’ share.

It had also alleged CTT had breached its fiduciary duty to Weida Works under the JVA. This had caused interalia loss of business opportunities pursuant to a licence agreement entered into between CTT and the original operators as well as damages (including aggravated and exemplary damages), interest; and costs.

Weida Works had filed its points of claim on Jan 3, and CTT had filed its reply on March 5,  2018.

 In the latest development, Weida said CTT’s 2018 counterclaim sought to declare the said JVA was not binding and/or void in law. 

It also said CTT sought refunds of all monies received from CTT save for telecommunication towers construction costs as well as to pay RM131.84mil being wrongful interest imposed by Weida Works with pre award and post arbitration award interest and costs. 

“This is despite CTT obtaining the full benefits of the JVA since its inception in 2005 till current date. 

“The arbitration has been fixed for hearing between July 18, 2018 to Aug 21, 2018.

Weida Works’ solicitors are of the conservative view that Weida Works has basis for the arbitration while in the current circumstances as known to Weida Works’ solicitors todate, CTT seems to have no basis for its allegations in its reply and counterclaim,” said Weida.




Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!

Common Tower Technology

   

Next In Business News

Sapura Energy secures PETRONAS contract for Pan Malaysia underwater services
YTL REIT to develop hotel in Japan for RM199mil
YTL stocks lift Bursa higher
China, Hong Kong stocks rise, led by property shares
QSR Brands temporarily shuts down over 100 KFC stores nationwide due to boycotts
Most Asian currencies muted; stocks gain ahead of Fed rate decision
Meta Bright secures RM28mil financing from AmBank
Tex Cycle partners Evolusi Bersatu for Sabah's first integrated waste management facility
Oil prices fall 1% on Israel-Hamas ceasefire talks, US inflation concerns
Boost EMS sector in Sarawak

Others Also Read