Rebuilt Penang Hill car park to open before CNY 2015, contractor slapped with RM210,000 penalty


  • Nation
  • Sunday, 09 Nov 2014

The new multi-level Penang Hill car park. - Starpix/LIM BENG TATT

GEORGE TOWN: The controversial car park at the foot of Penang Hill has finally been rebuilt after almost a year's delay and its contractor slapped with a RM210,000 penalty.

It is due to open to the public before Chinese New Year 2015, pending the connection of water and electricity supply and the issuance of the Certificate of Completion and Compliance (CCC) for the structure.

Limited time offer:
Just RM5 per month.

Monthly Plan

RM13.90/month
RM5/month

Billed as RM5/month for the 1st 6 months then RM13.90 thereafters.

Annual Plan

RM12.33/month

Billed as RM148.00/year

1 month

Free Trial

For new subscribers only


Cancel anytime. No ads. Auto-renewal. Unlimited access to the web and app. Personalised features. Members rewards.
Follow us on our official WhatsApp channel for breaking news alerts and key updates!
   

Next In Nation

It was a collective decision, says Zahid on settling suit against Muhyiddin
KKB polls: Four-cornered fight for Selangor state seat
Education institutions founded by MCA to collaborate with more Chinese universities
Man arrested, yaba pills worth over RM12,000 seized
Skywatchers out in force
Photo gallery: KKB by-election Nomination Day
KKB by-election: Live updates
AI content must not cross the line
The teacher who went the extra mile
Mum disowns son over loan shark debts

Others Also Read