Mall expected to be ready mid next year despite delay


Work in progress: After the laying of pipes for the centralised sewer system, the roofing project over the popular pedestrian mall can begin in January.

KUCHING: The start date of proposed roof over India Street Pedestrian Mall here has been delayed due to a sewerage project.

According to Kuching North City Hall (DBKU), the 120m roof over the historic street would only begin construction in January and still hope of meeting the original completion date of mid- year.