A TOTAL of eight out of the 95 overtaking lanes planned for the Pan Borneo trunk road in Sarawak had been completed, according to Infrastructure Development and Communications Minister Datuk Seri Michael Manyin.
Another two of such lanes were still under construction and 14 more were under design stages, he told the Assembly here yesterday.